Ulcombe Road

A complex build sequence and phasing made programming and planning an essential focus for the success of this project.

Surface water attenuation and a series of lagoons constructed in the early stages of the project assisted with the management of ground water through the designated construction phases.

Key Issues and how they were managed: The construction of the roads and drainage to maintain access for the superstructure works has been a major benefit for this project and the network of roads throughout.

Successful Outcomes and key targets and project measures:
Works are on target with the initial build programme and budget formulated prior to commencement.

Sector: Residential
Contract Value: £11.1m
Main Contractor: Chartway Group
Duration: 212 weeks
Type of works: Groundworks, highways & surfacing
Status: Current